Kleenheat, Gas Storage & Filling (Wavelane & Direct)

Site : Narngulu (Geraldton) – Process Plant

Replaced EEHA stop/ start station and motor on forklift refueling skid.  Included all new cabling and barrier glands.  Creation of Hazardous Area Verification Dosier.

Site : Churchlands Senior Highschool (Metro) – Workshop

Installed emergency shutdown solenoids for acetylene and LPG gas bottles for the workshop.

Site : Rottnest Island – LPG Facility

Undertook a detailed feasibility study for upgrading the Rottnest Island LPG facility.

Site : Northam Aerodrome – LPG Facility

Installation of >80kl LPG tank.  Electrical installation of pump motor, starter and earthing.

Beach Energy, Onshore Gas Production & Processing (HazTech/ GCo Electrical)

Site : Dongara – Gas Production Facility

As part of a project to install a new gas well head at Beharra Springs Gas Production facility near Dongara WA, we provided supervision for non-EEHA certified electricians to carry out the works.  This included training on how to use Ex rated barrier glands to ensure barrier integrity.
Once completed, we provided third party initial detailed inspection services for the entire new installation to ensure compliance to Australian Standards, client specifications and engineering drawings.  At the end of construction and pre-commissioning phases, our services were further utilised by Valmec (the construction contractor) for online commissioning and start-up processes.

Synergy, Power Station (HazTech Solutions)

Site : Kwinana – 2, Gas Fired GE Turbines and associated Gas Infrastructure

Undertook 4 yearly periodic EEHA inspections of electrical equipment in Hazardous Areas (250+), trialing SafeEx software-based system and demonstrated to Synergy the streamlining of future inspection campaigns.

Triangle Energy, Oil Production & Processing (HazTech Solutions/ Powertech)

Site : (Near) Dongara – Arrowsmith Oil Stabilisation Plant

Undertook 4 yearly periodic EEHA inspections of electrical equipment in Hazardous Areas (200+).  Developed a Punch list register of non-conformances with suggested remedial actions.  Provided EEHA advice and options going forward to assist with future inspection campaigns.  This included suggestions on implementing software-based inspections and a certified RFID tagging system.

BOC, Gas Production & Storage (for Selectek & Direct)

Site : Murrin Murrin (Minara Resources) Steam Methane Reformer producing Hydrogen & Air Separation Unit producing Oxygen and Nitrogen

Replaced Ex e local control stations around Hydrogen plant; replaced, programmed and tested/ commissioned safety instrumented trip relays, insulation resistance testing of HV motors, replaced HV insulators, disconnected and reconnected HV and LV motors, carried out micro-Ohm testing of electrical connections (Ductor testing) and assisted with replacing Emergency Shutdown System (ESD).

Site : Canning Vale Depot

Gas bottle buffer upgrade.  Disconnection of existing equipment and installation of new equipment.

Fortescue Future Industries (FFI) (for HazTech Solutions)

Site : Curtin University (Disconnections) & Aussie Fluid Power (Reconnections)

Systematically disconnected Hydrogen electrolyser and associated equipment ready for removal.  Systematically reconnected Hydrogen electrolyser and commissioned.  Tested, developed, altered, improved and (somewhat) redesigned Hydrogen electrolyser for FFI.  Disconnected again and installed as a containerised solution.

Elgas, LPG Gas Storage & Filling Depots                                                      

Site : Geraldton Depot, Kalbarri Depot, Denmark Depot, Narrogin Depot,
Bunbury Depot, Boddington Gas Storage, Canning Vale Depot and various warehouses and workshops in Perth Metro

Refurbishment of LPG tanks for forklift refueling; disconnections of LPG forklift refueling tanks, installation of LPG tanks including development of Hazardous Area Verification Dossiers (HA VD), maintenance including replacement of switches, motors, scales and level sensors at LPG refueling and gas filling depots and updating of existing HA VD, carry out testing of equipotential bonding at refueling depots and earth resistivity testing of earth electrodes.

GRP Tank Solutions, Tank Manufacturing

Site : Bibra Lake, Perth

FRP/ GRP Tank manufacturing facility; undertook 4 yearly periodic EEHA inspections, replaced Ex d resin heaters, replaced facility Ex dembq light fittings, attend to breakdowns, test and maintain earthing system to reduce the incidence of static and maintain integrity of the earthing system and surface resistance testing to IEC 66079.32.2 of carbon cloth coated hydrochloric acid tanks for supply to BHP’s Nickel West Kwinana facility.

Trident Fluid Systems, Offshore Services Provider

Site : Canning Vale Workshop, Perth

Termination of subsea cables from umbilical reeler to junction box using EEHA glands, termination of deck jumper cables using Trolex EEHA connectors and undertook an EEHA compliance review of hydraulic power unit.

ATCO, Power Station (HazTech Solutions)

Site : 2, Gas fired GE turbines and associated gas infrastructure KARRATHA

Undertook 3 yearly periodic EEHA inspection of all electrical equipment in Hazardous Areas (300+) within the gas fired power generation station in Karratha.  This inspection campaign also required detailed inspections to be conducted at a sample rate of 10%.

Kirkside, Chemical Storage Warehouse

Site : Osborne Park Warehouse, Perth

Reviewed Safety Data Sheets (SDS’s) for the chemicals being combined at the facility, reviewed the warehouse facility and layout, and undertook a risk assessment of current company practices and processes to determine the safest and most cost-effective solution for the client to comply with their EEHA obligations.  The resulting solution saved the client significant expenses by negating any current and future EEHA costs.

Ensign Energy, Onshore Drill Rigs Australia-wide

Site : Onshore Drill Rig in Canning Basin – East of Broome, WA

Site : Onshore Drill Rig in Cooper Basin – Moomba, SA

Site : Onshore Drill Rig in Perth Basin – Dongara, WA

Site : Onshore Drill Rig in Surat Basin, QLD

Recruited, selected and provided the best-fit, highly experienced Hazardous Area electricians for Ensign Energy’s onshore gas drill rig operations.  Under a labour hire arrangement with option to transfer to the client permanently, we have fulfilled multiple resourcing needs for the client to date (ongoing).

CSBP, Ammonium Nitrate Production (Techskills Australia)

Site : CSBP Kwinana – ANE (Ammonium Nitrate) Plant, WA

Subject Matter Expert (SME) on a CSBP Shutdown.  The role included providing technical support and mentoring to EEHA Inspectors and Rectification Workers carrying out close and detailed inspections and remediation works, as well as investigating IS circuits and carrying out calculations to ensure compliance.

Mineral Resources Limited, Lithium Mine(MOXI HA Services)

Site : Minerals Lithium Mine – Wodgina Port Hedland, WA

Carried out detailed EEHA inspections on instrumentation and motors, in preparation for re-start up of the plant which has been on Care and Maintenance. 

Minara Resources, Nickel Cobalt Mine(MOXI HA Services)

Site : Murrin Murrin Nickel Cobalt Mine, WA (Leonora/ Laverton)

Carried out detailed EEHA inspections on all electrical and instrumentation equipment on site.

Clean Energy Fuels Australia, Onshore LNG Process & Storage

Site : Kaolin and future West Gold Sites (4) – Gas Storage Facilities (5)

An ongoing project to establish LNG storage facilities at 5 CEFA sites in WA.  QETS’s team of EEHA site personnel undertook the installation of cable ladders, cables, instrumentation, motors and the control room on site.  Inclusive of the full wiring of control room sea containers and upgrades to MCC to facilitate the change from 22kW to 55kW motors.  All associated testing and commissioning activities.

Buru Energy, Onshore Oil Production

Site : Ungani Oil Process Facility

Hazardous Areas rectification works inspections and sign-off.  Testing and inspections of earthing and lightning protection system (LPS).  Engineering and design of rectifications for lightning protection system.

CBH, Grain Handling Depots (for Trinity MSAS)

Site : Metro Grain Centre Forrestfield, York Grain Depot

Disconnections and reconnections to facilitate the replacement of a conveyor tripper unit.  Ongoing provision of multiple EEHA qualified electricians for maintenance operations.

 Origin Energy, LPG Storage & Filling (for Wavelane)

Site : Linfox Hazlemere & Kewdale – LPG Forklift Refueling Station

Electrical installations, testing and commissioning.

Site : Pinjara Origin Energy Terminal

Carry out EEHA inspections and (pending) rectifications.

Site : Market City Canning Vale

Breakdowns on large LPG refueling station.  Rectification works ongoing.